Regulations on grid connected management of distributed phot
Time:2017-11-22Browse times:
The first is to further support Jiangsu province to accelerate the development of distributed photovoltaic power generation, specification of distributed PV grid management, improve the service level, according to the relevant national laws and regula

Chapter 1 General Provisions
 
 
The first is to further support Jiangsu province to accelerate the development of distributed photovoltaic power generation, specification of distributed PV grid management, improve the service level, according to the relevant national laws and regulations and technical standards, the national Power Grid Corp "on a distributed PV grid service work advice (Provisional)", "on the promotion of distributed photovoltaic power generation and network management advice (Interim)" and "distributed photovoltaic power generation connected to the distribution network related technical regulations (Provisional)", combined with the practice of Jiangsu power grid, according to an outside, the optimization process, simplify procedures, grid grid to improve the service efficiency principle, the enactment of this provision.
 
 
The second distributed photovoltaic power generation refers to the photovoltaic power generation project which is located near the user, which can be used locally, with 10 (20) kV and below voltage level connected to the grid, and the total installed capacity of single and network outlets is not more than 6 mw.
 
 
Third to 10 (20) access voltage level to 10 kV or above (20) kV voltage level to boost access but out of the photovoltaic power generation projects, photovoltaic power generation projects and individual outlets total installed capacity of 6 MW and above, according to the nature of the project (public power owned power plant power plant or enterprise), according to the national Power Grid Corp, the company management regulations related to the conventional power supply.
 
 
Fourth distributed photovoltaic power generation projects connected to public power grid, access system engineering and access to the public power grid transformation by the provincial company investment construction. The distributed photovoltaic power generation project connected to the user side is involved in the construction of the project owner, and the public power grid reconstruction caused by the access is partly invested by the power supply company. By the provincial company to invest in the construction of parts, the corresponding project in the year 10 (20) kV and below the distribution network project arrangements. The project involves materials according to the existing distribution network materials procurement mode into the company's unified material tender platform procurement, priority to consider the use of agreement inventory procurement.
 
 
Fifth distributed photovoltaic power generation projects and network power quality should meet the national standards, engineering design and construction should meet the "photovoltaic power station design specifications" and "photovoltaic power station construction specifications" and other national standards.
 
 
Sixth distributed photovoltaic power generation projects built in the user's internal site (access to the user side), the power generation can be all the Internet, all for their own or spontaneous use of the remaining power to the Internet, by the user's own choice, the lack of electricity users by the power grid enterprises. The upper and lower power grids are separately settled, and the electricity price is carried out by the government. The funds and additional parts of the private power consumption of the distributed PV power station are implemented according to the relevant policies of the government.
 
 
Seventh distributed photovoltaic power generation project free system reserve capacity fee. The power supply company does not charge any fees in the whole process of the acceptance of the grid connection application, the establishment of the access system scheme, the signing of the contract and agreement, the acceptance of the grid connection and the commissioning of the grid connection.
 
 
The second chapter management principle
 
 
Eighth distributed photovoltaic power generation project grid management work must fully implement the "four services" purpose, earnestly implement the national laws and regulations, standards, regulations and regulatory requirements related to power supply.
 
 
The ninth power supply companies should actively provide convenient conditions for the distributed photovoltaic power generation project to access the power grid, and open up a green channel for the access system construction. Establish an effective grid connected management system and coordination mechanism of distributed photovoltaic power generation project, formulate emergency plan for emergency service of photovoltaic power generation, implement service quality supervision and public opinion monitoring, properly and timely deal with complaints from project owners.
 
 
The third chapter management responsibilities
 
 
First, save the company's responsibility
 
 
Tenth development planning department is responsible for collecting and reporting information of distributed PV, grid information includes information related to various stages of pre construction, access, access and contract agreement, acceptance, parallel operation of distributed grid connected photovoltaic power generation projects; responsible for guiding the city signed a distributed photovoltaic power generation projects, the total generating capacity of the Internet purchase and sale electric contract.
 
 
Eleventh Sales Department (the agricultural department) is responsible for the service supervision, quality control and management assessment of the work at all levels of power supply company; responsible for the jurisdiction of distributed PV and consulting services to carry out the work of supervision and inspection, statistics and analysis.
 
 
Twelfth responsible for the operation and maintenance overhaul power grid project management network requirements involving clear distributed photovoltaic power generation projects; responsible for the formulation and improvement of distributed photovoltaic power generation project access technology standard or regulations; responsible for the development of distributed photovoltaic power generation projects and networks involved in management access engineering; responsible for the operation and management of distribution network provides for distributed photovoltaic power generation project related.
 
 
The thirteenth financial assets department is responsible for the formulation of distributed photovoltaic power generation project online power settlement operation measures; responsible for the payment of the distributed photovoltaic power generation.
 
 
The fourteenth economic and legal department is responsible for the legal guidance of purchasing and selling electricity contracts and dispatching grid connected agreements in distributed photovoltaic power generation projects.
 
 
The fifteenth dispatching control center is responsible for guiding the city company dispatching control center to carry out the grid connected dispatching agreement signing work.
 
 
Sixteenth power trading center is responsible for checking the distribution of electricity and electricity settlement of the distributed photovoltaic power generation project.
 
 
The seventeenth provincial research institutes are responsible for guiding the planning work of the distributed PV project access system of the local city company; guiding the acceptance of the distributed photovoltaic power generation project in the city and the city.


CONTACT US

ADD:Tangfang Road, Xinzhuang sub-district, Yixing city, Jiangsu Province, China

TEL:+86 510 81731999

FAX:+86 510 81731998

E-Mail:leonard@gsolar.com.cn

Visit Mobile Station
Copyright ©  2017-2025 JIANGSU GOODSUN NEW ENERGY CO.,LTD. Consulting Hotline:+86 510 81731999  Technical support:JOYON Power by DedeCms Technical support:JOYON